FREEPORT, Grand Bahama, January 17, 2024 — Lucaya Service Company (LUSCO) in a press release today shared an update on the progress of the Fortune Bay Canal Maintenance, Dredging and Jetty Repair Project.

Noting that Marine side activities are well advanced with the first of three dredging segments now completed, the release stated, “Excavation dredging has commenced at the second segment and near the entrance of the inlet.”

“The timetable for the completion of these critical works has been delayed by several factors, including: the impact of inclement weather, equipment challenges, the use of environmentally sensitive extraction techniques, and some requirements to revisit and expand the onshore staging areas,” said CEO Charisse Brown

The Lusco team continues to work alongside the GBPA’s Building and Development team in addition to its engaged engineering consultants and contractor to deliver the completed works in a safe manner whilst attempting to minimize disruption to local stakeholders.

“We are committed to completing this large and complex project as swiftly as possible in order to allow normal use of the inlet to restart,” Mrs. Brown said. “We thank our stakeholders for their patience and understanding, and remain open to handle any additional questions on a one on one basis an will continue to provide updates via LUSCO’s Facebook page.”

LUSCO continues to stress the importance of safety, urging all vessel operators to exercise extreme caution while navigating the Fortune Bay Canal area during both work and off-hours.

Mariners are advised to reduce speed within 1,000 feet of the channel inlet and jetty area, maintain a maximum speed of 4 KNOTS within the waterway, and steer clear of buoys, pilings, equipment, and work activities.